It is July 2018. Harvesting has not previously required resource consent. Will it under the NES-PF?
You are the woodlot planner. You did a harvest plan for a good-sized woodlot just prior to the NES-PF coming into effect. The questions below are a list of things you need to check out before meeting with your boss.
You are a forestry consultant asked by the landowner, Kotahi farms, for independent advice. The date is 12 June 2018 so the NES-PF is in force. Kotahi wants to log and replant 15 ha. You’ve got one of your staff to run MPI’s ESC and fish spawning tools, so you have on hand the relevant ESC and fish spawning maps (see page 3 and 4). For this scenario the land is in the yellow zone. Your staff also got a competent person to complete the wilding risk calculator and have confirmed there will be no problem to comply with the permitted activity conditions on wilding risk.
You will need to review the information and answer Kotahi’s questions.
keywords: pit-qfp-isr, grains
This document is part of a package of guidance developed by the Ministry for Primary Industries (MPI) to support the interpretation and implementation of the Resource Management (National Environmental Standards for Plantation Forestry) Regulations 2017 (NESPF).
This user guide is a manual for interpreting and implementing the Resource Management (National Environmental Standards for Plantation Forestry) Regulations 2017 (the NESPF). It supports the implementation of the NESPF by providing information and guidance on the regulations and is specifically targeted at regional councils, territorial authorities, and the forestry industry as the primary users of the NESPF.
Under the Agricultural Compounds and Veterinary Medicines (ACVM) Act 1997, all substances that are agricultural compounds must be registered unless exempted.